News

TYAZHMASH completed reconstruction of Belorechenskaya HPP

December 25, 2019

On March 30, 2017 JSC TYAZHMASH and the company GidroSpetsStroyMontazh (Volgodonsk) within the framework of the investment project “Reconstruction of Belorechenskaya HPP” signed an agreement for the supply of equipment for two hydraulic turbines of stations 1 and 3. The main customer was OOO LUKOIL Ecoenergo.

>Within the framework of the contract, JSC TYAZHMASH fully developed the technical documentation, manufactured and supplied two radial-axis turbines with complete electric cylinders, spare parts and mounting devices, as well as rendered services on installation supervision and equipment adjustment.

On December 9, 2019 at Belorechenskaya HPP in the presence of representatives of the customer OOO LUKOIL Ecoenergo, the general contractor HydroSpetsStroyMontazh and the manufacturing plant of JSC Tyazhmash complex tests of equipment for the hydro unit of station 3 were completed. The turbine was successfully tested within 72 hours. As a result, the declared guaranteed operational parameters of the equipment and its full compliance with the technical documentation requirements were confirmed. There were no claims from the customer, they were satisfied with the results.

All equipment for the hydrounit of station 3 was delivered in accordance with the contractual terms, and most of it arrived at the construction site of Belorechenskaya HPP ahead of schedule. By the present moment, the hydrounit of station 3 has been put into commercial operation. Thus, the investment project “Reconstruction of Belorechenskaya HPP” can be considered as successfully completed.